Unit Cost detail

Demolición Pavimento Asfaltico E0.21 M.

Owner: Geztio Latam

Find the detail of the cost of (m2) of Demolición Pavimento Asfaltico E0.21 M. . Materials, equipment, transport and labor required.

Materials
DescriptionUnitQuantityWasteValueSubtotal
Disco diamantado segmentado 14 pulg. para asfalto und 0.035.00 688,487.85 20,654.6355
AWaste 1,032.73
B
Waste + Material subtotal 21,687.3655
Equipment
DescriptionUnitQuantityProductionValueSubtotal
Herramienta menor % 1 10 6,815.9545 681.60
Cortadora de concreto día 1.00 75.00 124,152.00 1,655.36
Compresor con martillo neumatico 120 p hora 1.00 9.38 47,850.20 5,101.3006
C
Equipment subtotal 7,438.2606
Transportation
DescriptionUnitQuantityDistanceValueSubtotal
This Unit Cost does not include any transportation 0.00
D
Transportation subtotal 0.00
Labor
DescriptionTimeUnitQuantityProductionValueSubtotal
Cuadrilla 1:5 (oficial + 5 ayudantes) 100.00 día 1.00 75.00 511,196.59 6,815.9545
E
Labor subtotal 6,815.9545
F
(A + B + C + D + E) Direct cost 35,941.58

Frequently asked questions

What materials are used for m2 of Demolición Pavimento Asfaltico E0.21 M.?

  • 0.03 und of Disco diamantado segmentado 14 pulg. para asfalto

What equipment is used for m2 of Demolición Pavimento Asfaltico E0.21 M.?

  • 1.00 % of Herramienta menor
  • 1.00 día of Cortadora de concreto
  • 1.00 hora of Compresor con martillo neumatico 120 p

What labor is used for m2 of Demolición Pavimento Asfaltico E0.21 M.?

  • 1.00 día of Cuadrilla 1:5 (oficial + 5 ayudantes)

What is the price for m2 of Demolición Pavimento Asfaltico E0.21 M.?

35,941.58