Unit Cost detail

Nivelación y compactación de subrasante con rana

Owner: Geztio Latam

Find the detail of the cost of (m2) of Nivelación y compactación de subrasante con rana . Materials, equipment, transport and labor required.

Materials
DescriptionUnitQuantityWasteValueSubtotal
This Unit Cost does not include any material 0.00
AWaste 0.00
B
Waste + Material subtotal 0.00
Equipment
DescriptionUnitQuantityProductionValueSubtotal
Herramienta menor % 1 10 2,677.6965 267.77
Rana vibrocompactadora a gasolina hr 1.00 0.06 43,982.40 2,638.944
C
Equipment subtotal 2,906.714
Transportation
DescriptionUnitQuantityDistanceValueSubtotal
This Unit Cost does not include any transportation 0.00
D
Transportation subtotal 0.00
Labor
DescriptionTimeUnitQuantityProductionValueSubtotal
Cuadrilla 1:2 (oficial + 2 ayudantes) 100.00 día 1.00 0.01 267,769.65 2,677.6965
E
Labor subtotal 2,677.6965
F
(A + B + C + D + E) Direct cost 5,584.41

Frequently asked questions

What materials are used for m2 of Nivelación y compactación de subrasante con rana?

Nivelación y compactación de subrasante con rana doesn't require any materials.

What equipment is used for m2 of Nivelación y compactación de subrasante con rana?

  • 1.00 % of Herramienta menor
  • 1.00 hr of Rana vibrocompactadora a gasolina

What labor is used for m2 of Nivelación y compactación de subrasante con rana?

  • 1.00 día of Cuadrilla 1:2 (oficial + 2 ayudantes)

What is the price for m2 of Nivelación y compactación de subrasante con rana?

5,584.41