Unit Cost detail

Muro Estructural En Bloque M19 Abuzardado E0.19 M

Owner: Geztio Latam

Find the detail of the cost of (m2) of Muro Estructural En Bloque M19 Abuzardado E0.19 M . Materials, equipment, transport and labor required.

Materials
DescriptionUnitQuantityWasteValueSubtotal
Bloque m-19 0.39x0.19x0.19 m abuzardado und 12.005.00 5,200.00 62,400.00
AWaste 3,120.00
B
Waste + Material subtotal 65,520.00
Equipment
DescriptionUnitQuantityProductionValueSubtotal
This Unit Cost does not include any equipment 0.00
C
Equipment subtotal 0.00
Transportation
DescriptionUnitQuantityDistanceValueSubtotal
This Unit Cost does not include any transportation 0.00
D
Transportation subtotal 0.00
Labor
DescriptionTimeUnitQuantityProductionValueSubtotal
Cuadrilla 1:2 (oficial + 2 ayudantes) 100.00 día 1.00 0.13 267,769.65 34,810.0545
E
Labor subtotal 34,810.0545
F
(A + B + C + D + E) Direct cost 100,330.05

Frequently asked questions

What materials are used for m2 of Muro Estructural En Bloque M19 Abuzardado E0.19 M?

  • 12.00 und of Bloque m-19 0.39x0.19x0.19 m abuzardado

What equipment is used for m2 of Muro Estructural En Bloque M19 Abuzardado E0.19 M?

Muro Estructural En Bloque M19 Abuzardado E0.19 M doesn't require any equipment.

What labor is used for m2 of Muro Estructural En Bloque M19 Abuzardado E0.19 M?

  • 1.00 día of Cuadrilla 1:2 (oficial + 2 ayudantes)

What is the price for m2 of Muro Estructural En Bloque M19 Abuzardado E0.19 M?

100,330.05