Unit Cost detail

Localizacion Y Replanteo Topografico Edificacion

Owner: Geztio Latam

Find the detail of the cost of (m2) of Localizacion Y Replanteo Topografico Edificacion . Materials, equipment, transport and labor required.

Materials
DescriptionUnitQuantityWasteValueSubtotal
Pintura en esmalte gl 0.025.00 98,600.00 1,972.00
Estaca de madera h50cm und 0.505.00 3,200.00 1,600.00
Puntilla 1+ 1/2 a 3 pulg. lb 0.055.00 3,900.00 195.00
AWaste 188.35
B
Waste + Material subtotal 3,955.35
Equipment
DescriptionUnitQuantityProductionValueSubtotal
Herramienta menor % 1 10 1,678.3288 167.83
Estacion electronica y nivel día 1.00 300.00 87,941.00 293.1367
C
Equipment subtotal 460.9667
Transportation
DescriptionUnitQuantityDistanceValueSubtotal
This Unit Cost does not include any transportation 0.00
D
Transportation subtotal 0.00
Labor
DescriptionTimeUnitQuantityProductionValueSubtotal
Cuadrilla topografía (top + cad + 2 ayu) 100.00 día 1.00 300.00 503,498.63 1,678.3288
E
Labor subtotal 1,678.3288
F
(A + B + C + D + E) Direct cost 6,094.65

Frequently asked questions

What materials are used for m2 of Localizacion Y Replanteo Topografico Edificacion?

  • 0.02 gl of Pintura en esmalte
  • 0.50 und of Estaca de madera h50cm
  • 0.05 lb of Puntilla 1+ 1/2 a 3 pulg.

What equipment is used for m2 of Localizacion Y Replanteo Topografico Edificacion?

  • 1.00 % of Herramienta menor
  • 1.00 día of Estacion electronica y nivel

What labor is used for m2 of Localizacion Y Replanteo Topografico Edificacion?

  • 1.00 día of Cuadrilla topografía (top + cad + 2 ayu)

What is the price for m2 of Localizacion Y Replanteo Topografico Edificacion?

6,094.65