Unit Cost detail

Encofrado para columna en concreto

Owner: Geztio Latam

Find the detail of the cost of (m2) of Encofrado para columna en concreto . Materials, equipment, transport and labor required.

Materials
DescriptionUnitQuantityWasteValueSubtotal
Separol sika kg 0.065.00 27,298.60 1,637.916
Formaleta de madera m2 1.005.00 18,331.00 18,331.00
AWaste 998.45
B
Waste + Material subtotal 20,967.366
Equipment
DescriptionUnitQuantityProductionValueSubtotal
Parales telescopicos de 3 metros día 1.00 16.00 517.30 8,276.80
Herramienta menor % 1 10 13,330.5236 1,333.05
C
Equipment subtotal 9,609.85
Transportation
DescriptionUnitQuantityDistanceValueSubtotal
This Unit Cost does not include any transportation 0.00
D
Transportation subtotal 0.00
Labor
DescriptionTimeUnitQuantityProductionValueSubtotal
Cuadrilla 1:1 (oficial + 1 ayudante) 100.00 día 1.00 14.00 186,627.33 13,330.5236
E
Labor subtotal 13,330.5236
F
(A + B + C + D + E) Direct cost 43,907.74

Frequently asked questions

What materials are used for m2 of Encofrado para columna en concreto?

  • 0.06 kg of Separol sika
  • 1.00 m2 of Formaleta de madera

What equipment is used for m2 of Encofrado para columna en concreto?

  • 1.00 día of Parales telescopicos de 3 metros
  • 1.00 % of Herramienta menor

What labor is used for m2 of Encofrado para columna en concreto?

  • 1.00 día of Cuadrilla 1:1 (oficial + 1 ayudante)

What is the price for m2 of Encofrado para columna en concreto?

43,907.74