| Materials |
| Description | Unit | Quantity | Waste | Value | Subtotal | ||
|---|---|---|---|---|---|---|---|
| This Unit Cost does not include any material | 0.00 | ||||||
| A | Waste | 0.00 | |||||
B | Waste + Material subtotal | 0.00 | |||
| Equipment |
| Description | Unit | Quantity | Production | Value | Subtotal | ||
|---|---|---|---|---|---|---|---|
| Vibrador de concreto | día | 1.00 | 26.67 | 52,300.00 | 1,961.0049 | ||
| Herramienta menor | % | 1 | 10 | 6,997.6502 | 699.77 |
C | Equipment subtotal | 2,660.7749 | ||
| Transportation |
| Description | Unit | Quantity | Distance | Value | Subtotal | ||
|---|---|---|---|---|---|---|---|
| This Unit Cost does not include any transportation | 0.00 | ||||||
D | Transportation subtotal | 0.00 | ||
| Labor |
| Description | Time | Unit | Quantity | Production | Value | Subtotal | ||
|---|---|---|---|---|---|---|---|---|
| Cuadrilla 1:1 (oficial + 1 ayudante) | 100.00 | día | 1.00 | 26.67 | 186,627.33 | 6,997.6502 |
E | Labor subtotal | 6,997.6502 | ||
F | (A + B + C + D + E) Direct cost | 9,658.43 | ||