Unit Cost detail

Pavimento rígido MR 42 E=0.20 M

Owner: Geztio Latam

Find the detail of the cost of (m2) of Pavimento rígido MR 42 E=0.20 M . Materials, equipment, transport and labor required.

Materials
DescriptionUnitQuantityWasteValueSubtotal
Antisol blanco kg 0.220.00 7,445.00 1,637.90
Concreto premezclado mr 42 m3 0.210.00 459,816.00 96,561.36
AWaste 0.00
B
Waste + Material subtotal 98,199.26
Equipment
DescriptionUnitQuantityProductionValueSubtotal
Regla vibradora 4 mts dia 1.00 0.12 41,818.00 5,018.16
Formaleta metalica pavimento dia 1.00 2.00 2,975.00 5,950.00
Herramienta menor % 1 10 32,132.358 3,213.24
C
Equipment subtotal 14,181.40
Transportation
DescriptionUnitQuantityDistanceValueSubtotal
This Unit Cost does not include any transportation 0.00
D
Transportation subtotal 0.00
Labor
DescriptionTimeUnitQuantityProductionValueSubtotal
Cuadrilla 1:2 (oficial + 2 ayudantes) 100.00 día 1.00 0.12 267,769.65 32,132.358
E
Labor subtotal 32,132.358
F
(A + B + C + D + E) Direct cost 144,513.02

Frequently asked questions

What materials are used for m2 of Pavimento rígido MR 42 E=0.20 M?

  • 0.22 kg of Antisol blanco
  • 0.21 m3 of Concreto premezclado mr 42

What equipment is used for m2 of Pavimento rígido MR 42 E=0.20 M?

  • 1.00 dia of Regla vibradora 4 mts
  • 1.00 dia of Formaleta metalica pavimento
  • 1.00 % of Herramienta menor

What labor is used for m2 of Pavimento rígido MR 42 E=0.20 M?

  • 1.00 día of Cuadrilla 1:2 (oficial + 2 ayudantes)

What is the price for m2 of Pavimento rígido MR 42 E=0.20 M?

144,513.02