Unit Cost detail

Cuneta en concreto LD=1.00 M E=0.10 M

Owner: Geztio Latam

Find the detail of the cost of (m) of Cuneta en concreto LD=1.00 M E=0.10 M . Materials, equipment, transport and labor required.

Materials
DescriptionUnitQuantityWasteValueSubtotal
This Unit Cost does not include any material 0.00
AWaste 0.00
B
Waste + Material subtotal 0.00
Equipment
DescriptionUnitQuantityProductionValueSubtotal
Herramienta menor % 1 10 38,252.8071 3,825.28
C
Equipment subtotal 3,825.28
Transportation
DescriptionUnitQuantityDistanceValueSubtotal
This Unit Cost does not include any transportation 0.00
D
Transportation subtotal 0.00
Labor
DescriptionTimeUnitQuantityProductionValueSubtotal
Cuadrilla 1:2 (oficial + 2 ayudantes) 100.00 día 1.00 7.00 267,769.65 38,252.8071
E
Labor subtotal 38,252.8071
F
(A + B + C + D + E) Direct cost 42,078.09

Frequently asked questions

What materials are used for m of Cuneta en concreto LD=1.00 M E=0.10 M?

Cuneta en concreto LD=1.00 M E=0.10 M doesn't require any materials.

What equipment is used for m of Cuneta en concreto LD=1.00 M E=0.10 M?

  • 1.00 % of Herramienta menor

What labor is used for m of Cuneta en concreto LD=1.00 M E=0.10 M?

  • 1.00 día of Cuadrilla 1:2 (oficial + 2 ayudantes)

What is the price for m of Cuneta en concreto LD=1.00 M E=0.10 M?

42,078.09