Unit Cost detail

Afirmado E=0.10 M compactado con rana

Owner: Geztio Latam

Find the detail of the cost of (m2) of Afirmado E=0.10 M compactado con rana . Materials, equipment, transport and labor required.

Materials
DescriptionUnitQuantityWasteValueSubtotal
Afirmado y/0 sucio mt m3 0.130.00 70,210.00 9,127.30
Agua lt 4.005.00 5.00 20.00
AWaste 1.00
B
Waste + Material subtotal 9,148.30
Equipment
DescriptionUnitQuantityProductionValueSubtotal
Rana vibrocompactadora a gasolina hr 1.00 0.08 43,982.40 3,518.592
Herramienta menor % 1 10 8,033.0895 803.31
C
Equipment subtotal 4,321.902
Transportation
DescriptionUnitQuantityDistanceValueSubtotal
This Unit Cost does not include any transportation 0.00
D
Transportation subtotal 0.00
Labor
DescriptionTimeUnitQuantityProductionValueSubtotal
Cuadrilla 1:2 (oficial + 2 ayudantes) 100.00 día 1.00 0.03 267,769.65 8,033.0895
E
Labor subtotal 8,033.0895
F
(A + B + C + D + E) Direct cost 21,503.29

Frequently asked questions

What materials are used for m2 of Afirmado E=0.10 M compactado con rana?

  • 0.13 m3 of Afirmado y/0 sucio mt
  • 4.00 lt of Agua

What equipment is used for m2 of Afirmado E=0.10 M compactado con rana?

  • 1.00 hr of Rana vibrocompactadora a gasolina
  • 1.00 % of Herramienta menor

What labor is used for m2 of Afirmado E=0.10 M compactado con rana?

  • 1.00 día of Cuadrilla 1:2 (oficial + 2 ayudantes)

What is the price for m2 of Afirmado E=0.10 M compactado con rana?

21,503.29