Unit Cost detail

Relleno Con Material Comun Compactado

Owner: Geztio Latam

Find the detail of the cost of (m3) of Relleno Con Material Comun Compactado . Materials, equipment, transport and labor required.

Materials
DescriptionUnitQuantityWasteValueSubtotal
Arena lodosa de playa m3 1.255.00 30,000.00 37,500.00
AWaste 1,875.00
B
Waste + Material subtotal 39,375.00
Equipment
DescriptionUnitQuantityProductionValueSubtotal
Herramienta menor % 1 10 5,409.4873 540.95
Rana vibrocompactadora 8 hp día 1.00 15.00 93,114.00 6,207.60
C
Equipment subtotal 6,748.55
Transportation
DescriptionUnitQuantityDistanceValueSubtotal
This Unit Cost does not include any transportation 0.00
D
Transportation subtotal 0.00
Labor
DescriptionTimeUnitQuantityProductionValueSubtotal
Ayudante 100.00 día 1.00 15.00 81,142.31 5,409.4873
E
Labor subtotal 5,409.4873
F
(A + B + C + D + E) Direct cost 51,533.04

Frequently asked questions

What materials are used for m3 of Relleno Con Material Comun Compactado?

  • 1.25 m3 of Arena lodosa de playa

What equipment is used for m3 of Relleno Con Material Comun Compactado?

  • 1.00 % of Herramienta menor
  • 1.00 día of Rana vibrocompactadora 8 hp

What labor is used for m3 of Relleno Con Material Comun Compactado?

  • 1.00 día of Ayudante

What is the price for m3 of Relleno Con Material Comun Compactado?

51,533.04